Upgrade of Muizenberg beachfront under way

The refurbishment of the Muizenberg beachfront commences this week. The informal gravel parking area along the railway line on the western side of Surfer’s Corner will be closed for the next few months. There will be no access to the St James Walkway from Surfer’s Corner, and the public is advised to follow the detour signage to and from the underpass at Bailey’s Cottage and the rail level crossing at the beachfront instead.

The refurbishment of the Muizenberg beachfront entails major upgrades to public amenities and replacing the aged seawalls.

The western side of Surfer’s Corner, next to the railway line, will be impacted first as from this week. Work on the small parking area on the seaside of the Muizenberg Civic Centre will follow soon after.

  • The surf and beach itself will remain open and accessible at all times, however, work areas will be cordoned off in the interest of public safety
  • General work will take place from Monday to Saturday, from 07:00 to 17:00
  • Some work may happen after hours, depending on the tides and the stage of the project
  • Parking along the beachfront will be a challenge during busy times, given that the informal gravel parking area along the railway line will be closed to the public until further notice
  • Visitors are advised to anticipate congestion and delays to and from Beach Road

‘We will try mitigate the impact, still, a project of this magnitude will cause inconveniences. I request users to please adhere to the signage, to avoid the work areas and to keep their pets away from these in the interest of safety. We are counting on the public’s support and collaboration. I also want to thank all stakeholders in advance for their understanding, and encourage residents, local businesses, and other interested parties to join the available forums for regular updates and where concerns can be addressed,’ said the City’s Deputy Mayor and Mayoral Committee Member for Spatial Planning and Environment, Alderman Eddie Andrews.

What is next:

  • The informal gravel parking area along the railway line will be closed to the public, and fenced off
  • The small parking area located on the seaside of the Muizenberg Civic Centre is also impacted, and thus temporarily closed to the public
  • There will be no access to the St James Walkway from Surfer’s Corner. Signage will redirect users to the detour to and from the railway underpass at Bailey’s Cottage and the rail level crossing at the beachfront
  • Construction vehicles will be travelling to and from the construction area to deliver materials on a daily basis
  • Dust, noise, and traffic delays associated with construction work should be anticipated
  • Preliminary hand excavations to locate the existing underground services and foundations will commence from Monday, 10 February 2025, on the western side of Surfer’s Corner
  • Underground services will be realigned in the informal gravel parking area, and then the construction of the rock revetment at the start of the St James Walkway will commence

Stay informed

  • Look out for the public information displays at various points at the Muizenberg beachfront, these include artist impressions of the refurbishment and design
  • Scan the QR code to sign up for updates, and more information about the project
  • Sign up by using the following link: https://forms.office.com/r/8rARD9z8SM
  • Send an email to muizenberg@chand.co.za
To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

Entrepreneur completes business park 54% under budget in project-management triumph

COMPLETING a project on time and within budget is a difficult achievement in the notoriously variable construction industry. Doing it 54% under budget is...

Vinyl flooring expert transitions from Polyflor SA to Polysales

By Diane Silcock Alongside its rebrand, Polysales has expanded its vinyl flooring offerings to include an exciting new range of price-competitive luxury vinyl tiles. POLYFLOR South...

MUST READ

Industrial equipment rental leader Rand-Air transforms industry

By Diane Silcock WITH over 50 years of experience in the industrial equipment rental market, Rand-Air, part of the global Atlas Copco Group within the...

RECOMMENDED

Cape Business News
Follow us on Social Media