Concor in complex HVAC installation at Eastgate

To allow Eastgate Shopping Centre in Gauteng to upgrade its heating, ventilation and air conditioning (HVAC) facilities for greater energy and water efficiency, Concor is carefully strengthening the structure on which the heavy new chillers will rest. 

Concor Contract Manager Martin Muller explains that the HVAC system is located on top of a building on the centre’s roof parking area, in which tenants are active – and who need to continue trading during the renovation. Aside from the technical elements of the contract, therefore, clear and ongoing communication with the client and the tenants is a crucial aspect of success. 

The structure is being strengthened to ensure it can safety carry the seven 10 tonne HVAC chillers which will be installed on the roof top building.

“The construction work includes the demolition of an existing roof, walls and slab above tenants,” says Muller. “The structure will then be strengthened to ensure it can safely carry the seven 10 tonne HVAC chillers which are to be installed on the roof top building.” 

Due to the presence of a tenant running a call centre in the adjacent building, demolition can only take place outside of normal working hours. He highlights the importance of Concor’s safety culture in ensuring safe working practices at night.

What is important is for the considerable load of the new installation to be effectively transferred into the centre’s existing concrete columns under the roof parking – and hence down into the foundations. This is being done through the construction of interlinking stub columns which will create a grid to support the chillers. These columns are being cast systematically, working in a direction of priority for the HVAC specialists – so they can start their installations on the network of support steelwork and grating that Concor will provide.

The construction of interlinking stub columns will create a grid to support the chiller, with columns are being cast systematically in a direction of priority for the HVAC specialists so that work can begin.

The new structure will also include a transformer room, and a perimeter louvre closure around the HVAC area. At about 3,5 metres high, the louvre will improve the roof top aesthetics by concealing the installation from view. Concor’s team and subcontractors receive working-at-height training and work strictly according to safety protocols – especially since the HVAC rooms are 8,5 metres above ground on one side of the structure and 20 metres high on the other. Completing the project will be a steel roof, louvres to allow fresh air to cool the installation, access doors and a steel staircase. 

Contact information 

On behalf of Concor Construction  

www.concor.co.za

To enquire about Cape Business News' digital marketing options please contact sales@cbn.co.za

Related articles

The suspension of loadshedding has surpassed the 250-day mark, resulting in year-on-year diesel savings of R16.99 billion

The investment in the Generation Recovery Plan continues to yield consistent results, with loadshedding suspended for 254 consecutive days since 26 March 2024. This...

Opinion Piece: The importance of distribution in energy delivery in shaping the future of sub-Saharan Africa

By Lee Mbenge, Divisional Chief Executive Officer at ACTOM (Pty) Ltd The Transmission and Distribution (T&D) of energy are the critical links connecting power generation...

MUST READ

South Africa’s economy facing optimistic future

KPMG shares insights from their South Africa Economic Outlook In search of fiscal consolidation Positive post-election sentiment coupled with improved energy availability and reduced inflation...

RECOMMENDED

Cape Business News
Follow us on Social Media